Project planning lessons from a Wyndham City Council engineer

Diraj Ranjit
Nov 10
3 min read

Updated: Nov 12

When a council project goes well, you don't see the planning behind it.

That's one of the things Liam Collins said when I sat down with him for the first episode of my Lessons Learnt series. Liam is a senior project engineer at Wyndham City Council, which takes in Werribee, Point Cook and a big part of Melbourne's west. Over about 10 years he's gone from water into transport, through design, into project management and now strategic planning. So he's worked the project life cycle from the end back to the start.

Here's what stuck with me, and what we do with it at CBD.

Four project management lessons from Liam Collins of Wyndham City Council: planning, slack, handover, soft skills



1. Planning pays, but you never see it

"Putting in a lot of effort in the planning phases of a project, I think, always pays dividends."

Liam's point is that when a job runs smoothly, the planning is invisible. You only notice it when things go wrong.

Civil construction project planning chart: the cost of a change rises from planning to design, build and handover

I've seen the same on jobs since 2010. The hours spent upfront are the cheapest hours on the whole project. Skip them and you pay later in variations, delays and a crew waiting on an answer. That's money that buys the community nothing.



2. Build slack into the program

Liam called it optimism bias.

"You put in really tight time frames with no slack... no factors for anyone getting sick or wet weather or anything like that, and thinking that you can achieve it day on day, week on week, and it just doesn't happen."
Construction program comparison for project management: no slack runs late, a program with slack finishes on time

Liam's fix for optimism bias

  1. Plan from what you've actually achieved before.

  2. Tell your stakeholders early.

  3. Hold the line when the pressure comes.

  4. Track the job closely enough that you see it slipping early, and do something about it.

On a tender the pressure is to sharpen everything, including the program. But a program with no slack just pushes the problem down the track, and it usually comes back as a variation. The contractor, that's us, pays, and the council and us wear it with the community. No one wins.



3. Handovers have to outlast the people

Some of Liam's projects run 5, 7, 9 years.

"People do come and go, so making sure that there's a sort of smooth transition between roles and phases is critical."

He sets up the governance from the start. Clear roles and responsibilities, a simple org structure, so everyone knows their place. And he puts experienced people in early to plan out each stage. It doesn't have to be in great detail.

Council project handover diagram: project leads change over a multi-year civil project while the handover page stays

That's why we put together the two templates below after our chat.



4. Lean on experience, and don't forget the soft skills

His advice to a young engineer: find the guru in the office and lean on them. Even when you think you know the answer, getting it checked gives you confidence.

And on young engineers with a good solution: "They might have a good solution, but they just can't sell it." If you can't bring the stakeholders with you, you'll fail. "Doesn't matter how good the idea is."

Liam Collins of Wyndham City Council on soft skills: a good solution fails if you can't sell it to stakeholders



What we do with it in civil design and construction

Bridge piers and headstock formwork on a civil design and construct bridge job in Queensland
A bridge job in Queensland

On a bridge job in Queensland, for example, the bearings came from specialist overseas suppliers. We checked them at the supplier before they shipped and again once they landed at specialist testing facilities in Sydney. Two checks, so a problem shows up in a test lab and not on site.

Civil construction quality checks on bridge bearings at the overseas supplier and a specialist testing facility in Sydney

Because design and construction sit in one team, the plan, the build and the handover stay connected. What the project learns doesn't fall through the gap between contracts.

The planning and the risk workshop is the cheapest and therefore the highest ROI work on the project.



Free project handover templates

Free project handover template and asset handover form for council civil construction projects, editable Word files

Project Handover Page

One page that travels with the project, so what the project knows stays with it when people move on.


Asset Handover Form

Moves a finished project into the asset register with the full picture, including cost by component for capitalisation.




Watch the full conversation

The full interview with Liam is on my LinkedIn.

Watch the full interview with Wyndham City Council senior project engineer Liam Collins on LinkedIn
Tap to watch on LinkedIn


Thanks again Liam for being so open.

If you deliver council projects, how do you hand a project over when the lead moves on?